Use the following data for problems 37 to 40. Activity Activity Predecessor Optimistic Time Most Likely Time Pessimistic Time A -- 2 5 9 B

Use the following data for problems 37 to 40.

Activity Activity Predecessor Optimistic Time Most Likely Time Pessimistic Time
A -- 2 5 9
B -- 14 15 22
C A 1 7 9
D B 12 18 24
E C, D 3 6 9
F C, D 10 12 18
G E, F 8 19 20
H E, F 3 4 5

  1. The critical path for the project?
    1. A, C, E, H
    2. B, D, F, H
    3. B, D, F, G
    4. All activities are on the critical path due to the variable activity completion times

  1. The expected time for activity C is?
    1. 6.33
    2. 7.02
    3. 9.00
    4. 1.06

  1. What is expected project completion time?
    1. 55.0
    2. 64.0
    3. 71.0
    4. 43.0

  1. What is the variance for the project?
    1. 3.4
    2. 5.6
    3. 7.4
    4. 11.6

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Cases An Active Learning Approach

Authors: Mark S. Beasley, Frank A. Buckless, Steven M. Glover, Douglas F. Prawitt

2nd Edition

0130674842, 978-0130674845

Students also viewed these Mathematics questions