Question
Use the following data for questions 39 and 40. Note, all times are in days. Normal time Crash time Normal Cost Crash Cost Crash cost/pd
Use the following data for questions 39 and 40. Note, all times are in days.
| Normal time | Crash time | Normal Cost | Crash Cost | Crash cost/pd | Crash by | Crashing cost |
Project | 42 | 28 |
|
|
|
|
|
A | 2 | 2 | 200 | 200 | 0 | 0 | 0 |
B | 5 | 3 | 450 | 550 | 50 | 2 | 100 |
C | 8 | 4 | 360 | 720 | 90 | 4 | 360 |
D | 12 | 8 | 860 | 1000 | 35 | 4 | 140 |
E | 4 | 2 | 400 | 450 | 25 | 0 | 0 |
F | 8 | 6 | 720 | 820 | 50 | 2 | 100 |
G | 9 | 3 | 1500 | 1900 | 66.67 | 2 | 133.33 |
H | 15 | 10 | 1645 | 2245 | 120 | 2 | 240 |
I | 6 | 2 | 342 | 642 | 75 | 0 | 0 |
J | 9 | 4 | 640 | 800 | 32 | 5 | 160 |
K | 12 | 7 | 1150 | 1350 | 40 | 5 | 200 |
L | 5 | 4 | 240 | 300 | 60 | 1 | 60 |
TOTALS |
|
| 8507 |
|
|
| 1493.33 |
Project time | Period cost | Cumulative cost | A | B | C | D | E | F | G | H | I | J | K | L |
42 | 0 | 0 |
|
|
|
|
|
|
|
|
|
|
|
|
41 | 50 | 50 |
| 1 |
|
|
|
|
|
|
|
|
|
|
40 | 50 | 100 |
| 2 |
|
|
|
|
|
|
|
|
|
|
39 | 60 | 160 |
| 2 |
|
|
|
|
|
|
|
|
| 1 |
38 | 67 | 227 |
| 2 |
| 1 |
|
|
|
|
| 1 |
| 1 |
37 | 67 | 294 |
| 2 |
| 2 |
|
|
|
|
| 2 |
| 1 |
36 | 67 | 361 |
| 2 |
| 3 |
|
|
|
|
| 3 |
| 1 |
35 | 67 | 428 |
| 2 |
| 4 |
|
|
|
|
| 4 |
| 1 |
34 | 72 | 500 |
| 2 |
| 4 |
|
|
|
|
| 5 | 1 | 1 |
33 | 130 | 630 |
| 2 | 1 | 4 |
|
|
|
|
| 5 | 2 | 1 |
32 | 130 | 760 |
| 2 | 2 | 4 |
|
|
|
|
| 5 | 3 | 1 |
31 | 130 | 890 |
| 2 | 3 | 4 |
|
|
|
|
| 5 | 4 | 1 |
30 | 130 | 1020 |
| 2 | 4 | 4 |
|
|
|
|
| 5 | 5 | 1 |
29 | 236.67 | 1256.67 |
| 2 | 4 | 4 |
| 1 | 1 | 1 |
| 5 | 5 | 1 |
28 | 236.67 | 1493.33 |
| 2 | 4 | 4 |
| 2 | 2 | 2 |
| 5 | 5 | 1 |
-
If the project has to be completed in 37 days, which activities should be crashed and for how long (Note: Please see the Crashing with POM-QM videos by Dr. Shafai in the Chapter 10 videos for this problem and problem 40)?
-
B for two days, D for three days, J for three days, and L for one day
-
B for two days, D for two days, J for two days, and L for one days
-
B for two days, D for four days, J for five days, K for one day and L for one day
-
No activities need to be crashed
-
You are being offered a bonus of $128 each day the project is completed early. How many days to you recommend crashing the project to?
-
Would never crash any project
-
Sometimes crashing a project is beneficial
-
Would randomly crash a project
-
Under no conditions crash this project finish in 42 days
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started