Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Use the following data to select one best answer to the following question: What is the gross profit for the low-rise office building project by

Use the following data to select one best answer to the following question: What is the gross profit for the low-rise office building project by applying Cash method for recognizing revenue? A construction company began operations on January 2, 2010. During the year the company was awarded one construction contract of low-rise office building. The company incurred $100,000 operating expenses for the year for which $75,000 has been paid while the balance is owed as of December 31, 2010. Project data is summarized for the project in the following paragraphs. The initial contract for the low-rise office building was signed on January 5, 2010 in the amount of $1,000,000. This amount included $800,000 for construction costs, $150,000 for overhead mark-up, and $50,000 for profit markup. The contractor broke ground on February 4, 2010. During the course of construction the client decided to upgrade the quality of the lighting and plumbing fixtures, resulting in a change order issued to the contractor in the amount of $100,000 on October 7, 2010. The change order price was calculated by the contractor as follows: $50,000 construction costs, $37,500 overhead markup, $12,500 profit markup. At the end of 2010, construction was not complete. However, the client was renting out office space to other entities as well as using some of the offices for the clients own business entity. Work remaining as of December 31, 2010 included surfacing the parking lot, erecting a portable parking attendants station, miscellaneous site concrete work and landscaping. This work was schedule to be completed by May 1, 2010, weather permitting. A summary of accounting data as of December 31, 2010 included total construction costs in the amount of $800,000 for which $600,000 was paid. The balance reflected unpaid bills for the month of December, and retention withheld on subcontracts throughout the course of the project. The total progress billing as of December 31, 2010 was $1,000,000 of which $900,000 was collected with the balance outstanding as retention receivable. The project manager estimated that given the work left to be completed, approximately $200,000 of construction cost would be incurred.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Behavioral Finance And Wealth Management

Authors: Michael M. Pompian

2nd Edition

1118014324, 978-1118014325

More Books

Students also viewed these Finance questions

Question

What community placements are available for practica?

Answered: 1 week ago

Question

plan how to achieve impact in practice from your research;

Answered: 1 week ago