Question
Use the following for questions 6 to 10 The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a
Use the following for questions 6 to 10 The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A 1 3 5 B 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5
What is expected completion time?
Using the data in problem 6, what is the critical path?
Using the data in problem 6, what is the project variance?
Using the data in problem 6, what is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)
Using the data in problem 6, what is the expected time for activity G?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started