Question
Use the following information for questions 86 through 88. Gorman Construction Co. began operations in 2010. Construction activity for 2010 is shown below. Gorman uses
Use the following information for questions 86 through 88.
Gorman Construction Co. began operations in 2010. Construction activity for 2010 is shown below. Gorman uses the completed-contract method.
Billings Collections Estimated
Contract Through Through Costs to Costs to
Contract Price 12/31/10 12/31/10 12/31/10 Complete
1 $3,200,000 $3,150,000 $2,600,000 $2,150,000
2 3,600,000 1,500,000 1,000,000 820,000 $1,880,000
3 3,300,000 1,900,000 1,800,000 2,250,000 1,200,000
88. Which of the following should be shown on the balance sheet at December 31, 2010 related to Contract 3?
a. Inventory, $200,000
b. Inventory, $350,000
c. Inventory, $2,100,000
d. Inventory, $2,250,000
Answer is A
**Can someone explain why?**
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started