Use the following information for the next three questions: Information on Red Hot Co.s construction contracts with customers which commenced during 2021 is shown below:
Use the following information for the next three questions:
Information on Red Hot Co.s construction contracts with customers which commenced during 2021 is shown below:
| Contract 1 | Contract 2 |
Contract price | 420,000 | 300,000 |
Costs incurred during the year | 240,000 | 280,000 |
Estimated costs to complete | 120,000 | 40,000 |
Progress billings | 150,000 | 270,000 |
Collections | 90,000 | 250,000 |
- At contract inception, Red Hot Co. assessed that its performance obligation in each of Contract 1 and Contract 2 is satisfied over time. Red Hot Co. uses the cost-to-cost method in measuring its progress on the contract. How much total profit (loss) is recognized from the two contracts in 2021?
- 40,000
- 20,000
- (20,000)
- 0
- At contract inception, Red Hot Co. assessed that its performance obligation in each of Contract 1 and Contract 2 is satisfied over time. However, Red Hot Co. determined that the outcome of the performance obligation in each of the contracts cannot be reasonably measured but contract costs incurred are recoverable. How much total profit (loss) is recognized from the two contracts in 2021?
- 40,000
- 20,000
- (20,000)
- 0
- At contract inception, Red Hot Co. assessed that its performance obligation in each of Contract 1 and Contract 2 is satisfied at a point in time, that is, when the construction is completed. How much total profit (loss) is recognized from the two contracts in 2021?
- 40,000
- 20,000
- (20,000)
- 0
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started