Use the following information to answer questions 15 - 18 Direct materials 5 kgs x $8 per kg Direct labour 4 hours x $12 per
Use the following information to answer questions 15 - 18
Direct materials 5 kgs x $8 per kg
Direct labour 4 hours x $12 per hour
Variable overheads $16 per hour
Overhear absorption rate $4 per labour hour
Budgeted output in January was 1,200 units.
1,300 units produced in February with the following results:
Direct materials used 6 600 kgs costing $50,160
Direct labour 5 330 hours costing $65,026
Actual variable overhead $26 650
What is the company's Materials Price Variance?
A. $800 unfavourable
B. $800 favourable
C. $2,640 unfavourable
D. $2,640 favourable
What is the company's materials usage variance?
A. $800 unfavourable
B. $800 favourable
C. $2,640 unfavourable
D. $2,640 favourable
What is the company's Labour Rate Variance?
A. $1,066 unfavourable
B. $1, 066 favourable
C. $1,560 favourable
D. $1,560 unfavourable
What is the company's Variable Overhead Efficiency Variance?
A. $520 favourable
B. $520 unfavourable
C. $5,330 favourable
D. $5,330 unfavourable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started