Use the following information to answer questions 6-10. Tunnels R Us commenced the construction of a tunnel for the city of Sydney on 1 July

Use the following information to answer questions 6-10.

Tunnels R Us commenced the construction of a tunnel for the city of Sydney on 1 July 20X5. It was a fixed price contract with revenue of $85 million. The expected completion date is 30 June 20X8. It is expected to cost $74 million to construct. The following information relates to the tunnel construction:

Tunnels R Us uses the percentage of completion method based on cost to account for its construction contracts. Assume all estimates are reliable. Note that all figures are in $000.

What is the appropriate journal entry to record the contract revenue and contract expenses for the year ended 30 June 20X8?

For the year ending 30 June

20X6

20X7

20X8

Costs incurred to date

23680 47500 87000

Estimated cost to complete

50320 28500

Progress billings during the year

20000 50000 15000

Cash collected during the year

15000 52000 18000

Physical completion %

25

59 100

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Frank Woods Business Accounting Volume 2

Authors: Frank Wood, Alan Sangster

11th Edition

0273712136, 9780273712138

More Books

Students also viewed these Accounting questions

Question

What are all the ways you count or measure customer complaints?

Answered: 1 week ago

Question

Do your staff and customers know these examples?

Answered: 1 week ago