Use the following information to answer questions 6-10. Tunnels R Us commenced the construction of a tunnel for the city of Sydney on 1 July
Use the following information to answer questions 6-10.
Tunnels R Us commenced the construction of a tunnel for the city of Sydney on 1 July 20X5. It was a fixed price contract with revenue of $85 million. The expected completion date is 30 June 20X8. It is expected to cost $74 million to construct. The following information relates to the tunnel construction:
Tunnels R Us uses the percentage of completion method based on cost to account for its construction contracts. Assume all estimates are reliable. Note that all figures are in $000.
What is the appropriate journal entry to record the contract revenue and contract expenses for the year ended 30 June 20X8?
For the year ending 30 June | 20X6 | 20X7 | 20X8 |
Costs incurred to date | 23680 | 47500 | 87000 |
Estimated cost to complete | 50320 | 28500 | |
Progress billings during the year | 20000 | 50000 | 15000 |
Cash collected during the year | 15000 | 52000 | 18000 |
Physical completion % | 25 | 59 | 100 |
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started