USE THE FOLLOWING INFORMATION TO ANSWER THE NEXT (3) QUESTIONS: During Year 1, Sparky Construction Company has a contract to construct a $4,500,000 high-rise apartment

image text in transcribed
image text in transcribed
USE THE FOLLOWING INFORMATION TO ANSWER THE NEXT (3) QUESTIONS: During Year 1, Sparky Construction Company has a contract to construct a $4,500,000 high-rise apartment building at an estimated cost of $4,000,000. The contract is to start in July of Year 1 and the high-rise apartment building is to be completed in October of Year 3. The following data pertain to the construction period (Note: by the end of Year 2, Sparky has revised the estimated total cost from $4,000,000 to $4,050,000) Year 1 Year 2 Year 3 Costs to Date $1,000,000 $2,916,000 $4,050,000 Estimated costs to complete Progress billings during S 900,000 $2,400,000 $1,200,000 the year Cash collected during the year $3,000,000 $1,134,000 $ - 0 $ 750,000 $1,750,000 $2,000,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting Volume 2

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield, Irene M. Wiecek, Bruce J. McConomy

13th Canadian Edition

1119740444, 9781119740445

More Books

Students also viewed these Accounting questions

Question

Convert the decimal 1 9 2 to binary

Answered: 1 week ago

Question

1.2 Describe who performs HRM.

Answered: 1 week ago