Use the following information to calculate the inventory reorder point: 730,000 units of material needed during the production period 365 day production period 3-day delivery
Use the following information to calculate the inventory reorder point: 730,000 units of material needed during the production period 365 day production period 3-day delivery period
Select one:
a.
2,000 units
b.
4,000 tons
c.
6,000 tons
d.
2,190,000 tons