Use the following network with activities and times estimated in daysto answer questions a through c. Activity Optimistic Most Probable Pessimistic A 2 5 6

Use the following network with activities and times estimated in daysto answer questions a through c.

Activity

Optimistic

Most Probable

Pessimistic

A

2

5

6

B

1

3

7

C

6

7

10

D

5

12

14

E

3

4

5

F

8

9

12

G

4

6

8

H

3

6

8

I

5

7

12

J

12

13

14

K

1

3

4

a. What are the critical path activities?
b. What is the expected time to complete the project?
c. What is the probability the project will take more than 28 days to complete?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International marketing

Authors: Philip R. Cateora, Mary C. Gilly, John L. Graham

15th Edition

9789339204464, 9780073529943, 9339204468, 007352994X, 978-0077446956

More Books

Students also viewed these Marketing questions

Question

Supply the intermediate mathematical steps in Justification 21.7.

Answered: 1 week ago

Question

=+Does this message make effective use of the AIDA model?

Answered: 1 week ago