Use the following planning chart to create the AON network and use it to answer the next 3 questions Activity Duration (days) Predecessor A
Use the following planning chart to create the AON network and use it to answer the next 3 questions Activity Duration (days) Predecessor A 5 B 8 A C 7 A D 6 A E 9 B,C,D F 10 D G 5 E,F Question 1 (4 points) What is the duration of this network. Question 1 (4 points) What is the duration of this network Question 2 (3 points) What is the earliest day task E can start PJ Question 3 (3 points) What us duration of this network if activity D takes 1 extra week to complete?