Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Use the following project status information to calculate each of the requested EVM numbers below. The project status is reported at the end of
Use the following project status information to calculate each of the requested EVM numbers below. The project status is reported at the end of week 13. Task A B C D E F Budget Cost $5,000 $8,500 $15,000 $10,000 $12,000 $15,000 Budget Duration 2 weeks 3 weeks 4 weeks 4 weeks 4 weeks 5 weeks a. (3 points) Planned value b. (3 points) Actual cost c. (3 points) Cost variance d. (3 points) Schedule variance e. (3 points) Cost performance index f. (3 points) Schedule performance index SPI E. (4 points) Budget at completion h. (4 points) Estimate to complete i. (4 points) Estimate at completion Status as of Week 13 100 percent complete, $5,000 100 percent complete, $9,000 75 percent complete, $14,000 50 percent complete, $9,000 Not started Not started
Step by Step Solution
★★★★★
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
a Planned Value PV PV is the sum of the budget costs of all tasks that have not started or are in pr...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started