Use the following project status information to calculate each of the requested EVM numbers below. The project status is reported at the end of

 

Use the following project status information to calculate each of the requested EVM numbers below. The project status is reported at the end of week 13. Task A B C D E F Budget Cost $5,000 $8,500 $15,000 $10,000 $12,000 $15,000 Budget Duration 2 weeks 3 weeks 4 weeks 4 weeks 4 weeks 5 weeks a. (3 points) Planned value b. (3 points) Actual cost c. (3 points) Cost variance d. (3 points) Schedule variance e. (3 points) Cost performance index f. (3 points) Schedule performance index SPI E. (4 points) Budget at completion h. (4 points) Estimate to complete i. (4 points) Estimate at completion Status as of Week 13 100 percent complete, $5,000 100 percent complete, $9,000 75 percent complete, $14,000 50 percent complete, $9,000 Not started Not started

Step by Step Solution

3.48 Rating (155 Votes )

There are 3 Steps involved in it

Step: 1

a Planned Value PV PV is the sum of the budget costs of all tasks that have not started or are in pr... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Methods of IT Project Management

Authors: Jeffrey Brewer, Kevin Dittman

2nd edition

1557536635, 978-0132367257, 0132367254, 978-1557536631

More Books

Students also viewed these Programming questions

Question

Define ethical behavior.

Answered: 1 week ago