Question

1 Approved Answer

Use the following to answer the next five questions: A Activity Optimistic Most Likely Pessimistic Time (ET) (s) B C Time estimates D 31 44

Use the following to answer the next five questions: A Activity Optimistic Most Likely Pessimistic Time (ET) (s) B C Time estimates D 31 44 48 22 Start E 40 50 60 31 b 49 56 72 34 A Expected Variance B End What is the estimated standard deviation of the expected time (in days) for the critical path?
image text in transcribed
image text in transcribed
Use the following to answer the next five questions: Time estimates Expected Variance Activity Optimistic Most Likely Pessirnistic Time (ET) (5) What is the estimated standard deviation of the expected time (in days) for the critical path? What is the estimated standard deviation of the expected time (in days) for the critical path? 8 20 25 5 2.83

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The ABCs Of Property Management

Authors: Ken McElroy

1st Edition

9781937832537

More Books

Students also viewed these General Management questions

Question

differentiate the function ( x + 1 ) / ( x ^ 3 + x - 6 )

Answered: 1 week ago

Question

In your opinion, how will HR change in the future? Why?

Answered: 1 week ago