Use the information for the question(s) below. Time 0 Time 1 Time 2 Time 3 Project A - 10,000 5,000 4,000 3,000 Project B -
Use the information for the question(s) below. Time 0 Time 1 Time 2 Time 3 Project A - 10,000 5,000 4,000 3,000 Project B - 10,000 4,000 3,000 10,000 If Wise Guy Inc. uses IRR rule to choose projects, which of the projects (Project A or Project B) will rank highest? O A. Project A B. Project B OC. Project A and Project B have the same ranking. D. Cannot calculate a payback period without a discount rate