Use the PERT Weighted average to estimate the duration of a task, in days, based on the following estimates: 4 = Optimistic Time in Days,

Use the PERT Weighted average to estimate the duration of a task, in days, based on the following estimates:
4= Optimistic Time in Days, 15- Most Likely Time in Days, 60- Pessimistic Time in Days
Provide your answer in whole numbers only, no decimals.
Your Answer:
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Of Art Galleries

Authors: Magnus Resch

3rd Edition

0714877751, 978-0714877754

More Books

Students also viewed these General Management questions

Question

What is the message frequency?

Answered: 1 week ago

Question

What is the schedule for this project?

Answered: 1 week ago

Question

Who is responsible for this project?

Answered: 1 week ago