Use this information for Flapjack Corporation to answer the question that follows. Flapjack Corporation had 7,680 actual direct labor hours at an actual rate of

Use this information for Flapjack Corporation to answer the question that follows.

Flapjack Corporation had 7,680 actual direct labor hours at an actual rate of $12.20 per hour. Original production had been budgeted for 1,100 units, but only 960 units were actually produced. Labor standards were 7.4 hours per completed unit at a standard rate of $13.00 per hour.

The direct labor time variance is

$6,113.28 unfavorable

$6,113.28 favorable

$7,488.00 unfavorable

$7,488.00 favorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Cost Accounting

Authors: Edward J. Vanderbeck

15th Edition

978-0840037039, 0840037031

More Books

Students also viewed these Accounting questions