Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98;
Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.03 Standard yards per unit: standard, 4.62 yards; actual, 5.06 yards Units of production: 9,100 Calculate the direct materials quantity variance.
a.$8,128.12 favorable
b.$7,927.92 unfavorable
c.$7,927.92 favorable
d.$8,128.12 unfavorable
Myers Corporation has the following data related to direct materials costs for November: actual costs for 4,600 pounds of material, $5.00 and standard costs for 4,470 pounds of material at $6.10 per pound.
What is the direct materials quantity variance?
a.$793 unfavorable
b.$5,060 favorable
c.$5,060 unfavorable
d.$793 favorable
Flapjack Corporation had 7,696 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 956 units were actually produced. Labor standards were 7.4 hours per completed unit at a standard rate of $12.96 per hour.
The direct labor rate variance is
$4,309.76 unfavorable
$4,309.76 favorable
$7,709.02 unfavorable
$7,709.02 favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started