Use this information to draw a network diagram. What is the expected duration of this project? Activity Immediate Predecessor Time A - 6 B -
Use this information to draw a network diagram. What is the expected duration of this project?
Activity | Immediate Predecessor | Time |
A | - | 6 |
B | - | 6 |
C | A, B | 16 |
D | B | 21 |
E | B | 10 |
F | C, D, E | 11 |
G | E | 16 |