Use your chosen method (other than linear regression) to forecast the percentages of work completed for months 16, 17, 18 and 19 Parameter estimates Saturation

Use your chosen method (other than linear regression) to forecast the percentages of work completed for months 16, 17, 18 and 19

Parameter estimates

Saturation (upper limit): 100% (project completed)

Midpoint (period or year): 9.5 (midpoint of the 19-month time horizon)

Time to grow from 10% to 90%: 16.5 (estimate of the time in months)

Start time: 1

End Time: 12

Value at beginning: 5.8

Value at end: 69.1

Months

S-Curve Values

1

9.417

2

11.947

3

15.044

4

18.773

5

23.174

6

28.249

7

33.943

8

40.143

9

46.676

10

53.324

11

59.857

12

66.057

13

71.751

14

76.826

15

81.227

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost And Value Management In Projects

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

2nd Edition

1119933544, 978-1119933540

More Books

Students also viewed these Accounting questions

Question

Explain the various ways to protect employees.

Answered: 1 week ago