Question

1 Approved Answer

Use your master production schedule in Table 1 and your MRP schedule for subassembly A to develop a material requirement plan ( MRP ) for

Use your master production schedule in Table 1 and your MRP schedule for subassembly A to
develop a material requirement plan (MRP) for component C using the lot size of 100 units
ordering policy.
Week 12345678
C
Lead Time: 2 weeks; On Hand: 45 units; Lot Size: 100 units;
Scheduled Receipts: 100 units in Week 1 and 100 units in Week 2
Gross Requirement
Scheduled Receipts
Projected On Hand
Net Requirements
PO Receipts
PO Releases
\table[[Week,Forecast,\table[[Customer],[Orders]],\table[[Projected],[On-Hand I],[nventory]],\table[[Net Inventory],[Before MPS]],MPS Start,MPS Receipt,\table[[Pvailable-to-],[nventory]]],[1,45,42,116,119,119,169,77],[2,45,38,231,238,238,288,200],[3,50,51,237,236,236,286,185],[4,60,356,251,276,276,326,241],[5,60,20,306,346,346,396,326],[6,50,15,381,416,416,466,401],[7,50,10,456,496,496,546,486],[8,45,45,501,501,501,551,456]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial And Accounting Principles In Islamic Finance

Authors: Samir Alamad

1st Edition

3030162982, 9783030162986

More Books

Students also viewed these Accounting questions