Using a triangular distribution formula, calculate this activity's cost estimate based on its three - point estimates: Optimistic = $ 2 , 0 0 0

Using a triangular distribution formula, calculate this activity's cost estimate based on its three-point estimates:
Optimistic =$2,000, Most Likely =$6,000, Pessimistic =$7,000
$5,500
$4,000
$6,000
$5,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Project Management

Authors: Timothy Kloppenborg

3rd edition

1285433351, 978-1285433356

More Books

Students also viewed these General Management questions

Question

Show that E[|X t+1 X t |F t ] =2 t holds.

Answered: 1 week ago

Question

What is the purpose of a retaining wall, and how is it designed?

Answered: 1 week ago

Question

How do you determine the load-bearing capacity of a soil?

Answered: 1 week ago

Question

what is Edward Lemieux effect / Anomeric effect ?

Answered: 1 week ago

Question

Define Management by exception

Answered: 1 week ago

Question

How do these conditions compare to the situation in China?

Answered: 1 week ago