Using Activity Based Costing: The Sompter Meter Company has improved its production planning schedule and would like to go this over with you from a
Using Activity Based Costing:
The Sompter Meter Company has improved its production planning schedule and would like to go this over with you from a financial standpoint.
The overhead cost is now being allocated based on the following table below:
Category | Plant and Equipment | Management | Purchasing | Sales and Shipping |
Total Cost | $700.00 | $2,200.00 | $600.00 | $1,500.00 |
Cost Allocation | Square feet | Labor hours | Purchase orders | Customer orders |
Total units used | 10000 | 2400 | 130 | 91 |
Product A | 1000 | 500 | 10 | 5 |
Product B | 2000 | 450 | 35 | 20 |
Product C | 3000 | 690 | 60 | 41 |
Product D | 4000 | 760 | 25 | 25 |
Determine the following based on the original production plan (product A -700, B-350, C-80 and D-42):
- Plan and equipment cost per product?
- Management costs per product?
- Purchasing Costs?
- Sales and shipping cost?
- Total allocated overhead cost?
- Profit per product?
- Unit profit per product?
- Total Profit of production plan?
- Do you have any suggestions for the Sompter Meter Companys production plan?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started