Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Using Microsoft Project answer the two questions below: Widget Toy Company Frank Girardi is a project manager at the Widget Toy Company ( Widget )

Using Microsoft Project answer the two questions below:
Widget Toy Company
Frank Girardi is a project manager at the Widget Toy Company (Widget), based on Kalamazoo,
Michigan. Frank just submitted a proposal to the new product review committee for funding of a
new children's toy based on a recently-released motion picture. Frank feels that if he can get the
product out for the Christmas buying season, Widget could take advantage of what he felt was
strong - but time-sensitive - market demand. It is now Monday, July 24,2023, and Frank knew
that he would have to have the project complete and the product in stores by Monday, November
20,2023 to meet the Black Friday shopping day (November 24th ).
Frank expected approval from the committee (i.e., Activity A in Table 1) at the end the week
(Friday, July 28th ), at which time he would begin coordinating the development and launch of the
new project. Since Frank is an experienced project manager, he has already laid out a
preliminary set of activities as shown in Table 1.
Based on his schedule, Frank felt that he could start work on some activities as soon as the
funding approval was received, such as finalizing the product design and placing an order for the
new equipment needed to produce the toy. However, many of the other activities had to be
performed sequentially. For example, worker training cannot be completed until the equipment
is installed and the dies and tools for the machine are built. Similarly, raw materials cannot be
ordered until the build dies/tools and advertising plan are completed (since both will influence
raw material selection for components of the toy).
At first glance, Frank is concerned about the delivery schedule. Currently, Frank only sees two
potential options for shortening the overall project duration:
1) After talking with the marketing manager, Margaret Cone, Frank learned that the he
could reduce the time spent on product advertising (Activity K in Table 1). However,
Margaret estimated that for each week of lost advertising, sales of the product would
decrease by 5%. Margaret also indicated that anything less than 8 weeks of advertising
would be insufficient for this type of new product.
2) Frank also spoke with Jeff Stevens, the production manager at the tool shop. While
the tool shop staff were accustomed to working a standard 5-day/40-hour work week (as
with all Widget employees), Jeff offered to speed up the dies/tools build up (Activity E)
through overtime. If the tool shop staff worked overtime each and every week (at an
additional total cost of $15,000), Jeff felt that they could reduce the time to complete the
building of the dies and tools by three weeks...if Frank could cover the additional cost.
Table 2 provides a high level estimate of projected financial information for the proposed new
toy.
Based on this information, develop a schedule in MS Project (or another scheduling tool of
your choosing) and answer the following questions:
1. When is the overall project slated to be completed? Will it finish by the stated deadline?
2. What actions (if any) does Frank need to take to make the project as successful as possible? If no actions are required, which tasks pose the greatest risk to the project and
why?
Widget Toy Company
Table 1: Activities for New Product Development
Activity Description Predecessor(s) Duration (Weeks)
A Obtain funding approval --1
B Finalize product design A 1
C Order new equipment A 1
D Receive new equipment C 7
E Build dies/tools B 10
F Install equipment D 1
G Train workers E, F 1
H De-bug process G 1
I Establish advertising plan B 1
J Finalize package/art work I 3
K Advertise J 12
L Order raw materials E, J 1
M Receive raw materials L 1
N Complete initial production H, M 3
O Ship product N 1
P Project completion K,O 0
Widget Toy Company
Table 2: Data from New Product Proposal
Projected sales (units)10,000
Proposed unit price $25.00
Projected sales (revenue) $250,000
Projected cost for 10,000 units $170,000
Projected profit for 10,000 units $80,000(32%)
Required profit margin for all new products 25%Widget Toy Company
Table 2: Data from New Product Proposal
Projected sales (units)10,000
Proposed unit price $25.00
Projected sales (revenue) $250,000
Projected cost for 10,000 units $170,000
Projected profit for 10,000 units $80,000(32%)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Concepts

Authors: Frank Rothaermel

2nd edition

77645065, 1259384071, 9780077645069, 978-1259384073

More Books

Students also viewed these General Management questions

Question

Explain all drawbacks of application procedure.

Answered: 1 week ago