Question

1 Approved Answer

Using Monte Carlo simulation the following data has been generated: The mean or expected cost of the project is found to be $138000. The variance

Using Monte Carlo simulation the following data has been generated: The mean or expected cost of the project is found to be $138000. The variance of the project cost is shown to be $64000000. The project team wants 99% confidence in having enough budget to cover the costs. If the baseline project budget given to the team is average or expected cost. What is the total needed budget to cover all the possible expenses? 


a. 226000 


b. 186000 


c. 162000 


d. 138000



Step by Step Solution

3.39 Rating (171 Votes )

There are 3 Steps involved in it

Step: 1

To solve this problem we need to understand the properties of a normal distribution Accord... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Business Reporting For Decision Making

Authors: Jacqueline Birt, Keryn Chalmers, Albie Brooks, Suzanne Byrne, Judy Oliver

4th Edition

978-0730302414, 0730302415

More Books

Students also viewed these General Management questions

Question

Explain the causes of indiscipline.

Answered: 1 week ago

Question

Explain the factors influencing wage and salary administration.

Answered: 1 week ago