Using MS Excel, build a Material Requirements Planning ( MRP ) record based on the following Master Production Schedule and Inventory Records File. MPS: Master

Using MS Excel, build a Material Requirements Planning (MRP) record based on the following Master Production Schedule and Inventory Records File.
MPS: Master Production Schedule
Finished Product: Rocking Chair
Date
April 5 April 12 April 19 April 26 May 3 May 10
Required Demand 75,75,75,100,100,125
Inventory Records File (IRF)
Scheduled Receipts
SR 200 on April 12
Initial Stock Balance (Beginning Inventory) BI 100
Lead Time
LT 2 weeks
Safety Stock
SS 10
Lot Size Discipline
Qd LFL
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

Chinese 1st Edition

7508679814, 978-7508679815

More Books

Students also viewed these General Management questions

Question

revenue recognition dilemma of vaccine stockpiles

Answered: 1 week ago

Question

Organizing Your Speech Points

Answered: 1 week ago