Question
1 Approved Answer
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months, and
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months, and the project variance is 16.
a) The probability that the project will be completed in 5 months = (round your response to four decimal places). b) The probability that the project will be completed in 20 months = (round your response to four decimal places). c) The probability that the project will be completed in 25 months = (round your response to four decimal places). d) The probability that the project will be completed in 37 months = (round your response to four decimal places). e) The due date that yields a 95% chance of completion = months (round your response to two decimal places)Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started