Using the AON diagram for this project Activity Description Predecessors Duration A Procure materials - 3 B Prepare site - 6 C Prepare request for
Using the AON diagram for this project
Activity Description Predecessors Duration A Procure materials - 3 B Prepare site - 6 C Prepare request for - 2 city approval D A 5 E Obtain city approval C 2 F Install connecting lies A 7 to main system G Erect building and B,D,E 4 equipment on siteStep by Step Solution