Question

1 Approved Answer

Using the complexity weighing scheme and the function point complexity weight table shown below, estimate the total function point count for a software development project.

Using the complexity weighing scheme and the function point complexity weight table shown below, estimate the total function point count for a software development project. Assume five function points equal one person a month and 4 people can work on the project.

a. What is the estimated project duration?

b. If each person charges $2500 per month, what is the total project cost?

c. If 12 people are available for the project, what is the estimated project duration?

Inputs 10 Rated Complexity low (2)
Outputs 15 Rated Complexity average (8)
Inquiries 12 Rated Complexity average (6)
Files 28 Rated Complexity high (10)
Interfaces 45 Rated Complexity high (15)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing a business risk appraoch

Authors: larry e. rittenberg, bradley j. schwieger, karla m. johnston

6th Edition

9780324645095, 324645090, 978-0324375589

Students also viewed these General Management questions

Question

Write a note on transfer policy.

Answered: 1 week ago

Question

Discuss about training and development in India?

Answered: 1 week ago

Question

Explain the various techniques of training and development.

Answered: 1 week ago

Question

Explain the various techniques of Management Development.

Answered: 1 week ago