Question
1 Approved Answer

Using the cumulative data from the IPMR below for WBS 1.1.5, calculate a formula-based estimate at completion (EAC) using the performance factor of cost performance

Using the cumulative data from the IPMR below for WBS 1.1.5, calculate a formula-based estimate at completion (EAC) using the performance factor of cost performance index times schedule performance index, or CPI x SPI.

WBS number 1.1.5, Armament, has a BCWS of 3049, a BCWP of 2807, an ACWP of 3262, a BAC of 3818, and an EAC of 4510

Please select answer from options below.

4538.2
4436.9
1275.4
4358.8

Please show work.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Old Money New Woman How To Manage Your Money And Your Life

Authors: Byron Tully

1st Edition

1950118010, 978-1950118014

More Books

Students explore these related Finance questions