using the cumulative data provided, calculate a formula-based estimate at completion using the performance factor of cost performance index schedule performance index, or CPI x
using the cumulative data provided, calculate a formula-based estimate at completion using the performance factor of cost performance index schedule performance index, or CPI x SPI.
(image description: WBS number 1.1.5, armament has a BCWS of 3049, a BCWP of 2807 an ACWP of 3262, a BAC of 3818, and an EAC of 4510)