Question
Reynolds Custom Builders (RCB) was established in 1987 by Avery Conway and initially built high-quality customized homes under contract with specific buyers. In the 2002s,
Reynolds Custom Builders (RCB) was established in 1987 by Avery Conway and initially built high-quality customized homes under contract with specific buyers. In the 2002s, Conway’s two sons joined the company and expanded RCB’s activities into the high-rise apartment and industrial plant markets. Upon the retirement of RCB’s long-time financial manager, Conway’s sons recently hired Ed Borke as controller for RCB. Borke, a former college friend of Conway’s sons, has been associated with a public accounting firm for the last 6 years.
Upon reviewing RCB’s accounting practices, Borke observed that RCB followed the completed-contract method of revenue recognition, a carryover from the years when individual home building was the majority of RCB’s operations. Several years ago, the predominant portion of RCB’s activities shifted to the high-rise and industrial building areas. From land acquisition to the completion of construction, most building contracts cover several years. Under the circumstances, Borke believes that RCB should follow the percentage-of-completion method of accounting. From a typical building contract, Borke developed the following data.
BLUESTEM TRACTOR PLANT | ||||||
Contract price: $8,337,000 | ||||||
2014 | 2015 | 2016 | ||||
Estimated costs | $1,826,010 | $2,705,200 | $2,231,790 | |||
Progress billings | 1,887,000 | 3,063,000 | 3,387,000 | |||
Cash collections | 1,775,000 | 2,805,000 | 3,280,000 |
(b) Using the data provided for the Bluestem Tractor Plant and assuming the percentage-of-completion method of revenue recognition is used, calculate RCB's revenue and gross profit for 2014, 2015, and 2016, under each of the following circumstances. (1) Assume that all costs are incurred, all billings to customers are made, and all collections from customers are received within 30 days of billing, as planned. (Round percentage of completion to 2 decimal places, e.g. 34.35% and final answers to 0 decimal places, e.g. 1,525.) Revenue Gross profit / (Loss) 2014 2015 2016 (2) Further assume that, as a result of unforeseen local ordinances and the fact that the building site was in a wetlands area, RCB experienced cost overruns of $875,000 in 2014 to bring the site into compliance with the ordinances and to overcome wetlands barriers to construction. (Round percentage of completion to 2 decimal pla es, e.g. 34.35% and final answers to 0 decimal places, e.g. 1,525.) Gross profit / (Loss) Revenue 2014 2015 2016 (3) Further assume that, in addition to the cost overruns of $875,000 for this contract incurred under part (b)(2), inflationary factors over and above those anticipated in the development of the original contract cost have caused an additional cost overrun of $1,076,000 in 2015. It is not anticipated that any cost overruns will occur in 2016. (Round percentage of completion to 2 decimal places, e.g. 34.35% and final answers to 0 decimal places, e.g. 1,525. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Revenue Gross profit / (Loss) 2014 2015 2016
Step by Step Solution
3.41 Rating (154 Votes )
There are 3 Steps involved in it
Step: 1
BLUESTEM TRACTOR PLANT Contract price 8337000 2014 2015 2016 Estimated ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started