Using the FCFS ( first come, first served ) decision rule for sequencing the jobs, the order is: Sequence Job 1 DE - 0 6

Using the FCFS(first come, first served) decision rule for sequencing the jobs, the order is:
Sequence
Job
1
DE-06
SY-11
CX-01
BR-02
RG-05
Part 2
2
RG-05
SY-11
CX-01
BR-02
DE-06
Part 3
3
BR-02
CX-01
RG-05
DE-06
SY-11
Part 4
4
BR-02
RG-05
DE-06
SY-11
CX-01
Part 5
5
RG-05
DE-06
BR-02
CX-01
SY-11
Part 6
The total flow time for the sequence developed using the FCFS rule= enter your response here days (round your response to two decimal places).
Part 7
The percentage utilization for the sequence developed using the FCFS rule= enter your response here%(enter your response as a percentage rounded to two decimal places).
Part 8
The average number of jobs in the system for the sequence developed using the FCFS rule= enter your response here jobs (round your response to two decimal places).
Part 9
The average tardiness(job lateness) for the sequence developed using the FCFS rule= enter your response here days (round your response to two decimal places).
Part 10
Using the EDD(earliest due date) decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were received):
Sequence
Job
1
BR-02
RG-05
DE-06
CX-01
SY-11
Part 11
2
SY-11
CX-01
DE-06
RG-05
BR-02
Part 12
3
BR-02
SY-11
CX-01
DE-06
RG-05
Part 13
4
BR-02
CX-01
DE-06
RG-05
SY-11
Part 14
5
RG-05
DE-06
BR-02
CX-01
SY-11
Part 15
The total flow time for the sequence developed using the EDD rule= enter your response here days (round your response to two decimal places).
Part 16
The percentage utilization for the sequence developed using the EDD rule= enter your response here%(enter your response as a percentage rounded to two decimal places).
Part 17
The average number of jobs in the system for the sequence developed using the EDD rule= enter your response here jobs (round your response to two decimal places).
Part 18
The average tardiness(job lateness) for the sequence developed using the EDD rule= enter your response here days (round your response to two decimal places).
Part 19
Using the SPT(shortest processing time) decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were received):
Sequence
Job
1
BR-02
DE-06
SY-11
CX-01
RG-05
Part 20
2
SY-11
RG-05
DE-06
CX-01
BR-02
Part 21
3
SY-11
CX-01
DE-06
RG-05
BR-02
Part 22
4
RG-05
CX-01
BR-02
SY-11
DE-06
Part 23
5
DE-06
SY-11
CX-01
BR-02
RG-05
Part 24
The total flow time for the sequence developed using the SPT rule= enter your response here days (round your response to two decimal places).
Part 25
The percentage utilization for the sequence developed using the SPT rule= enter your response here%(enter your response as a percentage rounded to two decimal places).
Part 26
The average number of jobs in the system for the sequence developed using the SPT rule= enter your response here jobs (round your response to two decimal places).
Part 27
The average tardiness(job lateness) for the sequence developed using the SPT rule= enter your response here days (round your response to two decimal places).
Part 28
Using the LPT(longest processing time) decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were received):
Sequence
Job
1
SY-11
BR-02
DE-06
CX-01
RG-05
Part 29
2
CX-01
RG-05
DE-06
SY-11
BR-02
Part 30
3
RG-05
BR-02
DE-06
SY-11
CX-01
Part 31
4
BR-02
DE-06
SY-11
RG-05
CX-01
Part 32
5
CX-01
SY-11
DE-06
RG-05
BR-02
Part 33
The total flow time for the sequence developed using the LPT rule= enter your response here days (round your response to two decimal places).
Part 34
The percentage utilization for the sequence developed using the LPT rule= enter your response here%(enter your response as a percentage rounded to two decimal places).
Part 35
The average number of jobs in the system for the sequence developed using the LPT rule= enter your response here jobs (round your response to two decimal places).
Part 36
The average tardiness(job lateness) for the sequence developed using the LPT rule= enter your response here days (round your response to two decimal places).
.
.
.
Question content area right
Part 1
The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241(day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241.
Job
Date Job Received
Due Date
Duration(days)
BR02
225
270
25
CX01
230
320
35
DE06
235
360
40
RG05
231
310
30
SY11
228
300
15

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Human Resource Management Employees And Employers In Action

Authors: Cynthia Fontelle, Louis Bevoc

1st Edition

1688510249, 978-1688510241

More Books

Students also viewed these General Management questions

Question

What factors seem to motivate most mergers?

Answered: 1 week ago