Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Using the following data, calculate the planned and actual monthly budgets through the end of June. Assume the project is planned for a 12-month duration

Using the following data, calculate the planned and actual monthly budgets through the end of June. Assume the project is planned for a 12-month duration and $250,000 budget. All costs are in $000.

Activity

Jan

Feb

Mar

Apr

May

Jun

Plan

% C

Value

Staffing

8

7

15

100

Blueprinting

4

6

10

100

Prototype Devlpmt

2

8

10

70

Full Design

3

8

10

21

67

Construction

2

30

32

25

Transfer

10

10

0

Monthly Plan

Cumulative

Monthly Actual

10

15

6

14

9

40

Cumul. Actual

Using the data from above, calculate the following values (show your work):

Schedule Variances

Planned Value of Work Scheduled (PV)

Earned Value (EV)

Schedule Performance Index (SPI)

Estimated Time to Completion

Cost Variances

Actual Cost of Work Performed (AC)

Earned Value (EV)

Cost Performance Index (CPI)

Estimated Cost to Completion

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Financial Accounting

Authors: Carl S. Warren, James M. Reeve

9th Edition

0324381921, 978-0324381924

More Books

Students also viewed these Accounting questions