Question
Using the following data, calculate the planned and actual monthly budgets through the end of June. Assume the project is planned for a 12-month duration
Using the following data, calculate the planned and actual monthly budgets through the end of June. Assume the project is planned for a 12-month duration and $250,000 budget. All costs are in $000.
Activity | Jan | Feb | Mar | Apr | May | Jun | Plan | % C | Value |
Staffing | 8 | 7 |
|
|
|
| 15 | 100 |
|
Blueprinting |
| 4 | 6 |
|
|
| 10 | 100 |
|
Prototype Devlpmt |
|
| 2 | 8 |
|
| 10 | 70 |
|
Full Design |
|
|
| 3 | 8 | 10 | 21 | 67 |
|
Construction |
|
|
|
| 2 | 30 | 32 | 25 |
|
Transfer |
|
|
|
|
| 10 | 10 | 0 |
|
|
|
|
|
|
|
|
|
|
|
Monthly Plan |
|
|
|
|
|
|
|
|
|
Cumulative |
|
|
|
|
|
|
|
|
|
Monthly Actual | 10 | 15 | 6 | 14 | 9 | 40 |
|
|
|
Cumul. Actual |
|
|
|
|
|
|
|
|
|
Using the data from above, calculate the following values (show your work):
Schedule Variances |
| |
| Planned Value of Work Scheduled (PV) |
|
| Earned Value (EV) |
|
| Schedule Performance Index (SPI) |
|
| Estimated Time to Completion |
|
|
|
|
Cost Variances |
| |
| Actual Cost of Work Performed (AC) |
|
| Earned Value (EV) |
|
| Cost Performance Index (CPI) |
|
| Estimated Cost to Completion |
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started