Using the following information, what is the peak manpower? Cost = $1,200,000 Total Manhours = 56,000 hours Duration = 70 weeks Group of answer choices
Using the following information, what is the peak manpower? Cost = $1,200,000 Total Manhours = 56,000 hours Duration = 70 weeks Group of answer choices 20 hours 800 hours 20 workers 800 workers 32 workers 32 hours