Using the following table, if the project team will work a standard week work and that all the tasks will start as soon as possible:

Using the following table, if the project team will work a standard week work and that all the tasks will start as soon as possible: 1. Draw the corresponding activity network 2. Show the critical path. 3. What is the minimum time required to finish the project? 4. If task C (Programming) is delayed for 2 weeks, will the project finish on time? Why? If task (D Telecoms) is delayed for 2 weeks, will the project finish on time? Why?

Activity Duration

(week) Precedents A Requirement Analysis 5 - B System design 15 A C Programming 25 B D Telecoms 15 B E Hardware Installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training and support 5 G I Handover and Go-Live 5 H

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Databases questions