Using the information displayed in the following table, identify the critical path. Activity Name Successor Duration A B, C, D 5 B E 2 C
Using the information displayed in the following table, identify the critical path.
Activity Name | Successor | Duration |
A | B, C, D | 5 |
B | E | 2 |
C | E | 10 |
D | E | 7 |
E | None | 2 |
a.
A-C-E
b.
A-D-E
c.
A-E-D
d.
A-B-E