Question

1 Approved Answer

Using the information in the table below, calculate the total maximum risk contingency for the project. You may fill in the blank cells in

image text in transcribed

Using the information in the table below, calculate the total maximum risk contingency for the project. You may fill in the blank cells in the table to help you with your calculations. Suppose that you had decided to simply estimate the risk contingency as 5% of the total base cost. Would you have overestimated or underestimated the appropriate amount of contingency compared the result from the expected net risk calculation? Element Clearing Excavation Compaction Handwork Landscaping Paving Base Max Cost Cost $3,694 $4,000 $21,296 $23,000 $2,945 $3,500 $1,750 $2,000 $8,722 $9,500 $105,633 $110,000 Max Risk % Probability 20% 20% 10% 5% 30% 40% Expected Net Risk

Step by Step Solution

3.46 Rating (153 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting An Integrative Approach

Authors: C J Mcnair Connoly, Kenneth Merchant

2nd Edition

099950049X, 978-0999500491

More Books

Students also viewed these Physics questions