Using the information provided in figure 9a, 9b, and 9c, what are the Total Earned Workhours for the Column Forms? Select one: a. 465 b.

Using the information provided in figure 9a, 9b, and 9c, what are the Total Earned Workhours for the Column Forms?

image text in transcribed

image text in transcribed

image text in transcribed

Select one:

a. 465

b. 19

c. 2,387

d. 27

Figure 9a Earned Workhour Report Information DESCRIPTUN QUANTITIES UNIT EXPENDED WORK HOURS WORK HOURS UNIT WORK HOURS PROJECTED BUDGET TO DATI EARNED BUXGETED BUDGET TO DATI WEEK COMPLETION TO DATI GAIN LOS Col. Forms 2499 87 112 SECA 17 27 Concrete 256 25 10 CY 40 85 360 Concrete Wa 451 30 34 CY 40 44 Footing Frms 210 SPCA 102 499 Wall Forms 25.560 1880 3090 SECA 364 5544 Figure 9b Labor Cost Report Information CODE DESCRIPTION EXPENDED COST UNIT OOST PROJECTED QUANTITIES BUXHET TOTAL BUDGET s TO DATE UNIT WEEK TO DATE BUDGET WEEK TO DATI COMPLETION GAN LOSS Col Forms 2499 87 SPCA 223 355 8022 Cance 256 25 40 CY 365 805 5490 Cance 453 30 34 CY 9669 Footing Form 2417 210 410 SECA 1038 8154 Wall Forms 25,560 1880 3090 SECA 3812 6855 903 70 Figure 9c Project Cost Summary Report Information CODE ITEM ORIGINAL ESTIMATE SCOPE CHANGE REVISED ESTIMATE EXPENDED COMMITTED . EXPEND CURRENT PROJECTION PROJECTED GAIN (LOSS) WEEK TO DATE 035600 PILES 6700 VLE (720) 5980 VLF 680 0 680 Works A18 WIR 33 WHR 16817 (1900) 0 1360 Material 45225 40550 10000 23470 33470 (4675) (1400) Equipment 16040 14640 7600 9360 16960 Subcontract 0 0 0 7000 0 7000 67973 25960 32830 38790 Figure 9a Earned Workhour Report Information DESCRIPTUN QUANTITIES UNIT EXPENDED WORK HOURS WORK HOURS UNIT WORK HOURS PROJECTED BUDGET TO DATI EARNED BUXGETED BUDGET TO DATI WEEK COMPLETION TO DATI GAIN LOS Col. Forms 2499 87 112 SECA 17 27 Concrete 256 25 10 CY 40 85 360 Concrete Wa 451 30 34 CY 40 44 Footing Frms 210 SPCA 102 499 Wall Forms 25.560 1880 3090 SECA 364 5544 Figure 9b Labor Cost Report Information CODE DESCRIPTION EXPENDED COST UNIT OOST PROJECTED QUANTITIES BUXHET TOTAL BUDGET s TO DATE UNIT WEEK TO DATE BUDGET WEEK TO DATI COMPLETION GAN LOSS Col Forms 2499 87 SPCA 223 355 8022 Cance 256 25 40 CY 365 805 5490 Cance 453 30 34 CY 9669 Footing Form 2417 210 410 SECA 1038 8154 Wall Forms 25,560 1880 3090 SECA 3812 6855 903 70 Figure 9c Project Cost Summary Report Information CODE ITEM ORIGINAL ESTIMATE SCOPE CHANGE REVISED ESTIMATE EXPENDED COMMITTED . EXPEND CURRENT PROJECTION PROJECTED GAIN (LOSS) WEEK TO DATE 035600 PILES 6700 VLE (720) 5980 VLF 680 0 680 Works A18 WIR 33 WHR 16817 (1900) 0 1360 Material 45225 40550 10000 23470 33470 (4675) (1400) Equipment 16040 14640 7600 9360 16960 Subcontract 0 0 0 7000 0 7000 67973 25960 32830 38790

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing And Assurance Services An Integrated Approach

Authors: Alvin A. Arens . Randal J. Elder . Mark S. Beasley

15th Global Edition

0273790005, 978-0273790006

More Books

Students also viewed these Accounting questions

Question

What are the different categories of financial instruments?

Answered: 1 week ago

Question

Write a program to check an input year is leap or not.

Answered: 1 week ago

Question

Write short notes on departmentation.

Answered: 1 week ago

Question

What are the factors affecting organisation structure?

Answered: 1 week ago

Question

What are the features of Management?

Answered: 1 week ago

Question

Briefly explain the advantages of 'Management by Objectives'

Answered: 1 week ago