Using the information provided in figure 9a, 9b, and 9c, what are the Total Earned Workhours for the Column Forms? Select one: a. 465 b.
Using the information provided in figure 9a, 9b, and 9c, what are the Total Earned Workhours for the Column Forms?
Select one:
a. 465
b. 19
c. 2,387
d. 27
Figure 9a Earned Workhour Report Information DESCRIPTUN QUANTITIES UNIT EXPENDED WORK HOURS WORK HOURS UNIT WORK HOURS PROJECTED BUDGET TO DATI EARNED BUXGETED BUDGET TO DATI WEEK COMPLETION TO DATI GAIN LOS Col. Forms 2499 87 112 SECA 17 27 Concrete 256 25 10 CY 40 85 360 Concrete Wa 451 30 34 CY 40 44 Footing Frms 210 SPCA 102 499 Wall Forms 25.560 1880 3090 SECA 364 5544 Figure 9b Labor Cost Report Information CODE DESCRIPTION EXPENDED COST UNIT OOST PROJECTED QUANTITIES BUXHET TOTAL BUDGET s TO DATE UNIT WEEK TO DATE BUDGET WEEK TO DATI COMPLETION GAN LOSS Col Forms 2499 87 SPCA 223 355 8022 Cance 256 25 40 CY 365 805 5490 Cance 453 30 34 CY 9669 Footing Form 2417 210 410 SECA 1038 8154 Wall Forms 25,560 1880 3090 SECA 3812 6855 903 70 Figure 9c Project Cost Summary Report Information CODE ITEM ORIGINAL ESTIMATE SCOPE CHANGE REVISED ESTIMATE EXPENDED COMMITTED . EXPEND CURRENT PROJECTION PROJECTED GAIN (LOSS) WEEK TO DATE 035600 PILES 6700 VLE (720) 5980 VLF 680 0 680 Works A18 WIR 33 WHR 16817 (1900) 0 1360 Material 45225 40550 10000 23470 33470 (4675) (1400) Equipment 16040 14640 7600 9360 16960 Subcontract 0 0 0 7000 0 7000 67973 25960 32830 38790 Figure 9a Earned Workhour Report Information DESCRIPTUN QUANTITIES UNIT EXPENDED WORK HOURS WORK HOURS UNIT WORK HOURS PROJECTED BUDGET TO DATI EARNED BUXGETED BUDGET TO DATI WEEK COMPLETION TO DATI GAIN LOS Col. Forms 2499 87 112 SECA 17 27 Concrete 256 25 10 CY 40 85 360 Concrete Wa 451 30 34 CY 40 44 Footing Frms 210 SPCA 102 499 Wall Forms 25.560 1880 3090 SECA 364 5544 Figure 9b Labor Cost Report Information CODE DESCRIPTION EXPENDED COST UNIT OOST PROJECTED QUANTITIES BUXHET TOTAL BUDGET s TO DATE UNIT WEEK TO DATE BUDGET WEEK TO DATI COMPLETION GAN LOSS Col Forms 2499 87 SPCA 223 355 8022 Cance 256 25 40 CY 365 805 5490 Cance 453 30 34 CY 9669 Footing Form 2417 210 410 SECA 1038 8154 Wall Forms 25,560 1880 3090 SECA 3812 6855 903 70 Figure 9c Project Cost Summary Report Information CODE ITEM ORIGINAL ESTIMATE SCOPE CHANGE REVISED ESTIMATE EXPENDED COMMITTED . EXPEND CURRENT PROJECTION PROJECTED GAIN (LOSS) WEEK TO DATE 035600 PILES 6700 VLE (720) 5980 VLF 680 0 680 Works A18 WIR 33 WHR 16817 (1900) 0 1360 Material 45225 40550 10000 23470 33470 (4675) (1400) Equipment 16040 14640 7600 9360 16960 Subcontract 0 0 0 7000 0 7000 67973 25960 32830 38790Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started