Using the information provided in Table 2, perform resource-leveling. Assume that each task can be performed independently
Fantastic news! We've Found the answer you've been seeking!
Question:
- Using the information provided in Table 2, perform resource-leveling. Assume that each task can be performed independently of the other tasks, and the project must be completed in 10 days
Table 2
Activity # | Activity Name | IP | Duration (D) | Required Resources |
1 | A1 | - | 4 | 2 |
2 | A2 | - | 3 | 1 |
3 | A3 | - | 3 | 3 |
4 | A4 | - | 4 | 2 |
5 | A5 | - | 3 | 1 |
6 | A6 | - | 3 | 3 |
Activity | Req. Res. | D | Total Res. Days | ||||||||||
A1 | 2 | 4 | |||||||||||
A2 | 1 | 3 | |||||||||||
A3 | 3 | 3 | |||||||||||
A4 | 2 | 4 | |||||||||||
A5 | 1 | 3 | |||||||||||
A6 | 3 | 3 | |||||||||||
Day => | |||||||||||||
Total Resources => | |||||||||||||
2.Use the information provided for a construction project in Table 3 to develop a resource-constrained plan. Assume that only three workers are available for each day.
Table 3
Activity # | IP | Duration (D) | Required Resources |
1 | - | 4 | 1 |
2 | - | 5 | 2 |
3 | 1 | 4 | 2 |
4 | 1,2 | 5 | 1 |
5 | 2 | 3 | 2 |
6 | 3, 4, 5 | 2 | 2 |
ID | Req. Res. | D | Slack | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
1 | 1 | 4 | |||||||||||||||||
2 | 2 | 5 | |||||||||||||||||
3 | 2 | 4 | |||||||||||||||||
4 | 1 | 5 | |||||||||||||||||
5 | 2 | 3 | |||||||||||||||||
6 | 2 | 2 | |||||||||||||||||
Total Res. Load | |||||||||||||||||||
Res. Available |
Posted Date: