Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Using the information provided in the table, the network diagram and the expected project completion time = 3 9 ?weeks: Activity Optimistic Time ( weeks
Using the information provided in the table, the network diagram and the expected project completion time ?weeks:
Activity
Optimistic Time
weeks
Most Likely Time
weeks
Pessimistic Time
weeks
A
B
C
D
E
F
G
H
A network diagram is shown for activities A to H ?There are four paths. Path one is A ?B ?D ?F ?H ?Path two is A ?B ?D ?G ?H ?Path three is A ?C ?E ?G ?H ?Path four is A ?C ?E ?F ?H
The critical path is ABDGH
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started