Question

1 Approved Answer

Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? A

   

Using the method of ES, EF, LS, and LF; (a) Complete the table below. (b) Find the shortest time to complete the project? A B C D E Activity t 5 4 3 3 2 LL (c) Determine the critical path? (d) State the non-critical activities. (e) What is the implication of allowing activity B to spend extra 2 days instead of the slack number of days given in the table. G 1 10 9 A 5 C 3 ES 5 2 D3 4 B 4 EF 19 E 2 F 10 LS LO 6 3 G 9 LF 19 5 Slack 1 Critical Y

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Based on the project network diagram provided lets solve each of the questions step by step using the Early Start ES Early Finish EF Late Start LS and Late Finish LF method a Complete the table below ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Methods of IT Project Management

Authors: Jeffrey Brewer, Kevin Dittman

2nd edition

1557536635, 978-0132367257, 0132367254, 978-1557536631

More Books

Students also viewed these Programming questions

Question

Explain what is meant by an Organization's risk utility.

Answered: 1 week ago