Question

1 Approved Answer

*** Using the Newsvendor model/formula of calculation *** A small retailer is considering various monthly plans for purchasing electricity. They can pre-purchase kWhs at the

*** Using the Newsvendor model/formula of calculation ***

A small retailer is considering various monthly plans for purchasing electricity. They can pre-purchase kWhs at the cost of 4.5 cents per kWh. If they don't use all of the kWhs they purchase, then there is no refund for the unused electricity. If they need more kWhs than they purchase, the extra kWhs are purchased at the rate of 6 cents per kWh. Their forecast for kWh usage per month is normally distributed with a mean of 6000 and a standard deviation of 2500.

Using the Newsvendor model/formula of calculation, answer the following questions:

1. What is the cost of over-estimation?

2. Consider the small retailer example above. What is the cost of under-estimation?

3. Consider the small retailer example above. What is the critical ratio?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

OM operations management

Authors: David Alan Collier, James R. Evans

5th edition

1285451376, 978-1285451374

More Books

Students also viewed these General Management questions

Question

How would you define treasury management?

Answered: 1 week ago