Question

1 Approved Answer

Using the priority list T 2 , T 1 , T 5 , T 4 , T 3 , T 8 , T 9 ,

Using the priority list T2, T1, T5, T4, T3, T8, T9, T7, T6, schedule the project below with two processors.
Task Time Required Tasks that must be completed first
T18
T22
T39
T412 T1, T2
T511 T2, T3
T69 T2
T711 T4, T5
T88 T4, T5
T94 T5, T6
Task 7 is done by
Select an answer
starting at time
Task 9 is done by
Select an answer
starting at time
The finishing time for the schedule is

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

=+1. Describe the value chain of the media industry!

Answered: 1 week ago

Question

=+3. Draw the submodels of an integrated business model!

Answered: 1 week ago