Question

1 Approved Answer

Using the spreadsheet, calculate the NPV of VLCT Project to Airbus if it builds the VLCT and Boeing does not. ONLY MODIFY THE YELLOW CELLS!

Using the spreadsheet, calculate the NPV of VLCT Project to Airbus if it builds the VLCT and Boeing does not.

ONLY MODIFY THE YELLOW CELLS!

assumptions:

Price per plane = $220m (add 2% inflation each year, midpoint of projected range from case)

Expected planes sold per year = 30 (just above analyst forecast of 25, below 747 average of 35/year)

Operating margin = 20% (less than 747's margin of 25% because of expected price competition)

Development cost = $12.5 Bn total (spread over 5 years of development, midway between $5 Bn and $20 Bn, pp. 3-4 of case)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Forecasting

Authors: John E. Hanke, Dean Wichern

9th edition

132301202, 978-0132301206

More Books

Students also viewed these Finance questions