Using the table below, determine the overall duration of the project. Activity Duration IPA A 2 none B 3 A C 2 A D 5

Using the table below, determine the overall duration of the project.
Activity Duration IPA
A 2 none
B 3 A
C 2 A
D 5 B, C
12 days
10 days
9 days
5 days