Variable cost per unit is budgeted to be $6.00 and fixed cost per unit is budgeted to be $3.00 in a period when 5,000 units
Variable cost per unit is budgeted to be $6.00 and fixed cost per unit is budgeted to be $3.00 in a period when 5,000 units are produced. If production is actually 4,500 units, what is the expected total cost of the units produced?
$45,000
$40,500
$43,500
$42,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1