Variance analysis, material and labor The following information is available for Mandalay Company: Actual Materials 12,000 pounds purchased at $2.50 per pound; used 10,500 pounds

Variance analysis, material and labor The following information is available for Mandalay Company:

Actual
Materials 12,000 pounds purchased at $2.50 per pound; used 10,500 pounds
Direct Labor 1,800 hours at $12 per hour
Units Produced 500
Standard
Materials 20 pounds per unit at a price of $2.20 per pound
Direct Labor 4 hours per unit at a wage rate of $10 per hour

(a) Determine the material price variance based on the quantity of materials purchased.

(b) Determine the material quantity variance.

(c) Determine the direct labor rate variance.

(d) Determine the direct labor efficiency variance.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Accounting With QuickBooks 2021

Authors: Donna Kay

20th Edition

1264069197, 9781264069194

More Books

Students also viewed these Accounting questions

Question

Explain the defenses available in a breach-ofwarranty case.

Answered: 1 week ago

Question

Were any of the authors students?

Answered: 1 week ago