Vaughn Manufacturing prepared a fixed budget of 80000 direct labor hours with estimated overhead costs of $240000 for variable overhead and $90000 for fixed overhead.
Vaughn Manufacturing prepared a fixed budget of 80000 direct labor hours with estimated overhead costs of $240000 for variable overhead and $90000 for fixed overhead. If Vaughn prepares a flexible budget at 73000 direct labor hours, what is the total overhead costs at this level of activity? $219000 $309000 $301125 $330000