Velocity and Cycle Time Kolby Company takes 36,000 hours to produce 144,000 units of a product. Required: What is the velocity? Cycle time? Round the
Velocity and Cycle Time Kolby Company takes 36,000 hours to produce 144,000 units of a product. Required: What is the velocity? Cycle time? Round the cycle time to two decimal places. Velocity units per hour Cycle time hour(s)